54890: 1997-013-25 EXP YKFP O&M LOWER YAKIMA SUPPLEMENTATION COMPLEX |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Shirley Alvarado | Yakama Confederated Tribes | Yes | Administrative Contact | shirley_alvarado@yakama.com | (509) 865-5121x6304 |
Dave Fast | Yakama Confederated Tribes | Yes | Technical Contact | fast@yakama.com | (509) 966-5291 |
Bill Fiander | Yakama Confederated Tribes | Yes | Contract Manager | bfiander@yakama.com | (509) 865-5121x6372 |
Andre L'Heureux | Bonneville Power Administration | Yes | COR | allheureux@bpa.gov | (503) 230-4482 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Jennifer Lord | Bonneville Power Administration | Yes | Env. Compliance Lead | jklord@bpa.gov | (503) 230-5192 |
Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
Mel Sampson | Yakama Confederated Tribes | No | Supervisor | mel@yakama.com | (509) 865-5121x6303 |
Adrienne Wilson | Yakama Confederated Tribes | Yes | Administrative Contact | Adrienne_Wilson@Yakama.com | (509) 865-5121x6306 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Effective implementation management, and timely contract administration | A: 119. Manage and Administer Projects | 06/30/2014 | 06/30/2014 | |
Timely and successful Environmental Compliance documentation and clearance | B: 165. Environmental Compliance Documentation and Clearance | 06/30/2014 | 06/30/2014 | |
Reintroduce coho to the Yakima Basin | C: 176. Reintroduction of Coho in the Yakima Basin (BY 2012) | 06/30/2014 | 06/30/2014 | |
Reintroduce coho to the Yakima Basin | D: 176. Reintroduction of Coho in the Yakima Basin (BY 2013) | 06/30/2014 | 06/30/2014 | |
Increase Yakima River Mainstem Fall Chinook through supplementation | E: 176. Supplementation to Increase Yakima Mainstem Fall Chinook (BY 2013) | 06/30/2014 | 06/30/2014 | |
Increase Yakima River Mainstem Fall Chinook through supplementation | F: 176. Supplementation to Increase Yakima Mainstem yearling Fall Chinook (BY 2012) | 05/31/2014 | 02/20/2014 | |
Produce Early Fall/Summer Chinook BY13 | G: 176. Produce Early Fall/Summer Chinook (sub-yearlings) BY 2013 | 06/30/2014 | 06/30/2014 | |
Operate and maintain LYRSR sites and facilities. | H: 61. Operate & Maintain the Prosser Hatchery, Marion Drain Hatchery and the Acclimation Sites | 06/30/2014 | 06/30/2014 | |
Maintain fish health of LYRSR project fish. | I: 60. USFWS to Maintain Fish Health: Lower Yakima River Supplementation and Research Facilities | 06/30/2014 | 06/30/2014 | |
Produce Monthly Reports | J: 141. Other Reports for BPA | 06/30/2014 | 06/30/2014 | |
Update the Annual Operation Plan & Annual Maintenance Plan | K: 174. Update the Annual Operation Plan & the Annual Maintenance Plan | 11/30/2013 | 11/06/2013 | |
Prepare Annual Report | L: 132. Prepare Annual Report (July 1, 2012 - June 30, 2013) | 03/31/2014 | 03/08/2014 | |
Delineate and Secure Perimeter of Marion Drain Hatchery Site | N: 171. [CCR-31314] Secure Perimeter of Marion Drain Hatchery Site: Road & Fence Construction / Realignment | 06/30/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Coho (O. kisutch) - Unspecified Population |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Manage and Administer Projects | 07/01/2013 | ||||||
B | 165 | Environmental Compliance Documentation and Clearance | 07/01/2013 | ||||||
C | 176 | Reintroduction of Coho in the Yakima Basin (BY 2012) | |||||||
D | 176 | Reintroduction of Coho in the Yakima Basin (BY 2013) | |||||||
E | 176 | Supplementation to Increase Yakima Mainstem Fall Chinook (BY 2013) | |||||||
F | 176 | Supplementation to Increase Yakima Mainstem yearling Fall Chinook (BY 2012) | |||||||
G | 176 | Produce Early Fall/Summer Chinook (sub-yearlings) BY 2013 | |||||||
H | 61 | Operate & Maintain the Prosser Hatchery, Marion Drain Hatchery and the Acclimation Sites | 11/25/2013 | ||||||
I | 60 | USFWS to Maintain Fish Health: Lower Yakima River Supplementation and Research Facilities | 03/27/2013 | ||||||
J | 141 | Other Reports for BPA | 07/01/2013 | ||||||
K | 174 | Update the Annual Operation Plan & the Annual Maintenance Plan | 07/01/2013 | ||||||
L | 132 | Prepare Annual Report (July 1, 2012 - June 30, 2013) | 07/01/2013 | ||||||
M | 185 | Periodic Status Reports for BPA | 07/01/2013 | ||||||
N | 171 | [CCR-31314] Secure Perimeter of Marion Drain Hatchery Site: Road & Fence Construction / Realignment | 02/28/2014 |